Vocus Sets November 4 Completion Date for Australia Singapore Cable Repairs

The operator expects to finalize permanent repairs to the ASC following the restoration of the Indigo West system. Services between Australia and Singapore remain impacted, though specific Layer 2 Ethernet routes remain operational.

Markdown · Transcript · MP3 · Subscribe

Situation

No model writes this section. Operator updates are quoted from each operator's own status page and dated as the operator dated them. 1 of these operator incidents or notices is new since the last brief (20 Sep 19:36 UTC). Lines marked Elsewhere are Cloudflare Radar's own outage annotations, from anywhere in the world, with the cause as Radar labels it; this archive attributes nothing to anyone. Latency is measured between cities, not on any named cable: several systems serve each route and traffic moves to a survivor within seconds of a fault. Detail is in Standing status at the end of the brief.

Today

Vocus expects to complete permanent repairs to the Australia Singapore Cable (ASC) by 4 November [1]. This follows the scheduled restoration of the Indigo West subsea cable on 24 October, which serves as a primary route between Australia and Singapore [1]. While the ASC fault continues to affect services, Vocus stated that Layer 2 Ethernet services via the Perth-Singapore route through Jakarta remain operational [1].

International Infrastructure Developments

The ACE Cable consortium selected Ciena to upgrade the Africa Coast to Europe (ACE) system to over 30 Tb/s using WaveLogic 6 Extreme coherent optics [2]. Meanwhile, Meta and its partners announced Petal, a petabit-class transoceanic cable between France and the United States, which is expected to enter service in 2029 using multi-core fiber technology [5]. In the South Atlantic, Fugro clarified that its vessel, Fugro Supporter, conducted a seabed survey off Argentina for a project contracted by SubCom, rather than the UK government [4].

Canalink completed the marine deployment of the Atlántica cable project in the Canary Islands, with the vessel Teliri installing 553 kilometers of cable to connect Gran Canaria, Fuerteventura, and Lanzarote [3]. To support growing installation demands, Jan De Nul ordered a second subsea trenching vessel capable of burying cables up to five metres deep [6].

Capacity Upgrades and Infrastructure Interdependencies

FLAG announced on 21 September 2026 that it is deploying Ciena WaveLogic 6 Extreme technology on its dedicated fiber pair within the ECHO submarine cable system [7]. The upgrade covers more than 16,000 kilometers of the trans-Pacific route connecting Singapore, Guam, and California, and is intended to support new 400GbE and 800GbE services for hyperscalers and cloud providers [7].

Additionally, the Submarine Telecoms Forum released Issue 150, which includes expert assessments on the intersection of offshore energy and submarine networks [8]. The publication highlights how fiber networks support oil, gas, and wind operations, while also addressing AI capacity, South Pacific resilience, and the SAEx East cable system [8].

Also noted

References

  1. Vocus expects ASC repairs to be completed on 4 November (telecompaper.com)
    telecompaper.com
  2. ACE Cable Selects Ciena for 30 Tb/s Upgrade (Submarine Telecoms Forum)
    subtelforum.com · Also reported by: capacityglobal.com
  3. Canalink Completes Atlántica Cable Deployment (Submarine Telecoms Forum)
    subtelforum.com
  4. Fugro Clarifies Argentina Telecom Cable Survey (Submarine Telecoms Forum)
    subtelforum.com
  5. Inside Petal: Building the World’s First Petabit-Class Transoceanic Subsea Cable (Meta, Engineering Connectivity blog)
    engineering.fb.com
  6. Jan De Nul Orders Second Subsea Trenching Vessel (marinelink.com)
    marinelink.com
  7. FLAG Launches 400GbE and 800GbE on Echo (Submarine Telecoms Forum)
    subtelforum.com
  8. SubTel Forum Issue 150, Offshore Energy OUT NOW! (Submarine Telecoms Forum)
    subtelforum.com
  9. Almost everything you do online crosses the seabed through cables about as thick as a garden hose, not satellites. There are roughly 1.5 million kilometres of them, and repair ships spend their ... (scienceblog.com)
    Published: 20 Sep 2026 · scienceblog.com · Claim type: analyst_assessment · Subject: analysis, precedent · Systems named: SMW4, IMEWE · Vessels named: KIS-ORCA · Jurisdictions: INT

Standing status

Operator incident timelines (quoted from each operator's own status page, not summarised by any model):

1 other open incident(s) on those pages name no tracked cable system and are not shown.

Also polled for changes, but carrying no incident listing, so nothing is said about their state: AJC — cable system maintenance, AJC — news, SUBCO, SUBCO — INDIGO West, SUBCO — OAC, Southern Cross Cable Network, Telstra — service status, Vocus — network status.

Incident threads:

Measured path state (RIPE Atlas traceroute over 24h, no model involved):

A corridor is a city pair, not a cable. Several systems serve each of these routes and IP routing does not reveal which one carries a packet, so a healthy corridor is not evidence that any particular cable is intact: traffic reroutes onto a survivor within seconds of a fault. Per-probe detail is in cablewatch segments.

Every cable route leaving the mainland (measured hourly, no model involved):

A route is a pair of places, not a cable: several systems serve most of these and IP routing does not reveal which one carried a packet, so a healthy route is not evidence that every cable on it is intact. A path counts as direct when it is within reach of the physical floor between the two places. Routes with no vantage at the far end are listed in latency_watch.yaml under uncovered.

Collection: 566 successful fetches in 24h, 45 errors across 10 source(s). Generated 2026-09-21 19:37 UTC.