## Situation

- **Australia Singapore Cable**: open since 4 Sep, 14 days, per Global Secure Layer. Operator status: Identified.  
  Latest update, 4 Sep 06:49 UTC (14 days ago): “We observed short flaps occurring on the ASC submarine cable system at 04/09/2026 03:50:33 UTC. However a hard down event followed at 04/09/2026 06:19:12 UTC Due to the Indigo West cable system also being offline for shunt fault repairs, traffic will take a longer path which will result in higher latency between Australia and Singapore. We are waiting for further information from Vocus regarding this outage. Information received will be shared via our status page.”
- **INDIGO West**: notice posted by Superloop, already on its page when monitoring began 14 Sep; the notice carries no date of its own.  
  Notice: “We are currently experiencing a service disruption affecting the Indigo West link due to instability. Our team is actively investigating and working to resolve the issue. Updates will be provided as more information becomes available. Support remains available via phone and email during this time.”
- **Measured latency** (RIPE Atlas, best measured path over 24 hours against each route's best sustained floor over 28 days): Perth to Singapore 187.6ms, up 141.0ms on its 46.6ms floor; Sydney to Japan 100.4ms, up 42.9ms on its 100.5ms floor; Sydney to Singapore 144.5ms, up 48.1ms on its 96.5ms floor.

<sub>No model writes this section. Operator updates are quoted from each operator's own status page and dated as the operator dated them. No operator has posted an update or a new notice on these since the last brief (17 Sep 19:36 UTC). Latency is measured between cities, not on any named cable: several systems serve each route and traffic moves to a survivor within seconds of a fault. Detail is in Standing status at the end of the brief.</sub>

## Executive summary

- The mercury.com.au reports a 180km subsea cable project is proceeding at Bellbuoy Beach without council approval [1].
- The Finnish coast guard, police, and armed forces conducted a live boarding exercise to improve underwater infrastructure protection [2].
- The FDD reports Russia's GUGI unit conducted a covert operation near Svalbard to simulate attacks on fiber cables [3].
- Analyst Emmerson Overell assesses that these simulations target maritime and space infrastructure to impact NASA's Near Space Network [3].
- EllaLink announced it successfully laid two branching units for future Brazilian Amazon connections during its Lum@link marine campaign [5].
- Taiwan's Ministry of Digital Affairs announced the Taiwan-Matsu No. 4 submarine cable is now in service [7].

## Today

A 180km subsea cable project is moving forward at Bellbuoy Beach despite the fact that it has not received council approval [1]. Themercury.com.au reports that the site was chosen for the landing point, though the lack of official local government consent remains a point of contention.

## Infrastructure Security and Sabotage Exercises

Finnish coast guard, police, and armed forces conducted a live exercise on September 17 involving the boarding and searching of a vessel in the Baltic Sea to improve response times for protecting underwater infrastructure [2]. The drill, which included officers fast-roping from helicopters, was designed to counter threats from divers, mini-submarines, and diving robots following several incidents since 2022 [2]. In the Arctic, the Foundation for Defense of Democracies (FDD) reports that Russia's GUGI unit conducted a covert operation near Norway’s Svalbard archipelago in spring 2026 to simulate attacks on fiber cables connecting the SvalSat ground station to mainland Norway [3]. Analyst Emmerson Overell assesses that these simulations target the interconnectedness of maritime and space infrastructure, noting that disruptions to these cables could impact NASA’s Near Space Network and human spaceflight missions [3].

## International Infrastructure Developments and Security Claims

EllaLink announced on September 14, 2026, that it successfully laid two branching units for future Brazilian Amazon connections during its Lum@link marine campaign [5]. Manufactured and installed by Alcatel Submarine Networks, these units are positioned at depths of 3,920 metres and 3,690 metres to eventually connect Salinópolis in Pará and São Luís in Maranhão to the Lum@link system [5]. The installation is designed to allow for future 17 Tbps capacity branches to join the main route, which extends from Cayenne in French Guiana to EllaLink's trunk off Fortaleza [5].

Separately, a senior defence contractor claims that recent alleged Russian attempts to sever undersea cables may be rehearsals intended to knock out the United Kingdom's internet [6]. The source provided limited detail, characterizing the claims as a potential threat to UK national infrastructure and connectivity [6].

## Regional Infrastructure Expansion and Policy

Taiwan's Ministry of Digital Affairs announced that the Taiwan-Matsu No. 4 submarine cable is now in service [7]. Built by Chunghwa Telecom, the nearly 300 km link connects the main island to Dongyin, Nangan, and Xiju, increasing aggregate Taiwan-Matsu transmission capacity to approximately 1.9 Tbps [7]. This system joins Taiwan-Matsu No. 2 and Taiwan-Matsu No. 3, with Taiwan-Penghu No. 4 and Penghu-Kinmen No. 4 expected to be completed by the end of the year [7].

In broader regional policy, Indonesia and India signed a five-year Memorandum of Understanding to collaborate on 4G, 5G, 6G, and quantum technologies, including disaster management communication systems [8]. Meanwhile, the Philippines is seeing U.S. support for new submarine cable and infrastructure projects in Subic Bay to counter Chinese influence [9]. These projects include the proposed Thailand-U.S. Submarine Cable System (THUS), which would connect Thailand to the U.S. via Indonesia, Malaysia, the Philippines, Singapore, and Vietnam [9].

## References

1. [Bellbuoy Beach chosen for 180km subsea cable despite having no council approval](https://www.themercury.com.au/news/tasmania/bellbuoy-beach-chosen-for-180km-subsea-cable-despite-having-no-council-approval/news-story/16852407d805ac4eed4f10772517ec84) (themercury.com.au)
   themercury.com.au
2. [Finnish Authorities Board Ship In Baltic Sea During Live Exercise To Protect Undersea Cables](https://www.marineinsight.com/finnish-authorities-board-ship-in-baltic-sea-during-live-exercise-to-protect-undersea-cables/?utm_source=rss&utm_medium=rss&utm_campaign=finnish-authorities-board-ship-in-baltic-sea-during-live-exercise-to-protect-undersea-cables) (Marine Insight)
   marineinsight.com
3. [Russia Is Practicing Attacks on Undersea Cables in the Arctic. The Consequences Could Reach Space.](https://www.fdd.org/analysis/2026/09/16/russia-is-practicing-attacks-on-undersea-cables-in-the-arctic-the-consequences-could-reach-space/) (fdd.org)
   fdd.org
4. [ESA awards $1.73m project to neXat for automated submarine cable backup](https://satelliteprome.com/news/esa-awards-1-73m-project-to-nexat-for-automated-submarine-cable-backup/) (satelliteprome.com)
   satelliteprome.com
5. [EllaLink Lays Brazilian Amazon Branching Units](https://subtelforum.com/ellalink-lays-brazilian-amazon-branching-units/) (Submarine Telecoms Forum)
   subtelforum.com
6. [Russia is ‘rehearsing’ attacks that could knock out the UK’s internet](https://metro.co.uk/2026/09/14/russia-rehearsing-attacks-knock-uks-internet-29603438/) (metro.co.uk)
   metro.co.uk
7. [Taiwan-Matsu No. 4 Cable Enters Service](https://subtelforum.com/taiwan-matsu-no-4-cable-enters-service/) (Submarine Telecoms Forum)
   subtelforum.com
8. [Indonesia, India Forge Stronger Partnership in Telecom Innovation](https://www.telecomreviewasia.com/news/industry-news/30308-indonesia-india-forge-stronger-partnership-in-telecom-innovation/) (Telecom Review Asia)
   telecomreviewasia.com
9. [Indo-Pacific 5x5: September 16th 2026 / Issue 419](https://indopacificinsights.substack.com/p/indo-pacific-5x5-september-16th-2026) (indopacificinsights.substack.com)
   Published: 16 Sep 2026 · indopacificinsights.substack.com · Claim type: official_statement · Subject: policy, analysis · Systems named: Thailand-U.S. Submarine Cable System (THUS) · Jurisdictions: TH, US, ID, MY, PH, SG (+1 more)

---

## Standing status

**Operator incident timelines** (quoted from each operator's own status page, not summarised by any model):

- **Australia Singapore Cable** · Global Secure Layer — network status · Identified, open since 4 Sep
  - `4 Sep 06:49 UTC` Identified: We observed short flaps occurring on the ASC submarine cable system at 04/09/2026 03:50:33 UTC. However a hard down event followed at 04/09/2026 06:19:12 UTC Due to the Indigo West cable system also being offline for shunt fault repairs, traffic will take a longer path which will result in higher latency between Australia and Singapore. We are waiting for further information from Vocus regarding this outage. Information received will be shared via our status page.
  <sub>page last checked 2026-09-18 17:17 UTC · https://www.gslstatus.com/incidents/wqmz5wt7l8qj</sub>
- **INDIGO West** · Superloop — outages · active notice, on the page when monitoring began 14 Sep 21:44 UTC (the page gives no date)
  - We are currently experiencing a service disruption affecting the Indigo West link due to instability. Our team is actively investigating and working to resolve the issue. Updates will be provided as more information becomes available. Support remains available via phone and email during this time.
  <sub>page last checked 2026-09-18 19:12 UTC · https://www.superloop.com/outages/</sub>

<sub>Also polled for changes, but carrying no incident listing, so nothing is said about their state: SUBCO, SUBCO — INDIGO West, Telstra — service status, Vocus — network status.</sub>

**Incident threads:**

- `perth_indigo_2026_08` (INDIGO West, INDIGO Central) — 15 documents, last 2026-09-15 (quiet 4d)

**Measured path state** (RIPE Atlas traceroute over 24h, no model involved):

- **perth to singapore** — best path **187.6ms, +141.0ms on its best sustained 46.6ms**; typical path 273.5ms (+72.8ms per probe against its own history, 21 probes); ocean crossing 150.0ms; queuing 0.7ms; 28 days of history; clean crossing (21 probe(s), 39 reading(s) excluded as below the corridor's physical floor)
- **sydney to japan** — best path 100.4ms; typical path 177.6ms (+42.9ms per probe against its own history, 17 probes); ocean crossing 133.2ms; queuing 0.5ms; 28 days of history; clean crossing (17 probe(s))
- **sydney to nz** — best path 26.8ms; typical path 34.4ms (-0.0ms per probe against its own history, 8 probes); ocean crossing 28.0ms; queuing 0.2ms; steady against 28 days of history; clean crossing (8 probe(s))
- **sydney to singapore** — best path **144.5ms, +48.1ms on its best sustained 96.5ms**; typical path 225.7ms (+28.1ms per probe against its own history, 21 probes); ocean crossing 153.2ms; queuing 0.7ms; 28 days of history; clean crossing (21 probe(s))

<sub>A corridor is a city pair, not a cable. Several systems serve each of these routes and IP routing does not reveal which one carries a packet, so a healthy corridor is not evidence that any particular cable is intact: traffic reroutes onto a survivor within seconds of a fault. Per-probe detail is in `cablewatch segments`.</sub>

**Every cable route leaving the mainland** (measured hourly, no model involved):

- **Australia to Guam** — best 70.5ms against a 52.0ms floor; 12/24 paths direct (normally 8) <br><sub>Australia-Japan Cable (AJC), Japan-Guam-Australia South (JGA-S), PIPE Pacific Cable-1 (PPC-1)</sub>
- **Dili to Australia** — best 48.9ms against a 7.1ms floor; 3 paths measured <br><sub>Timor-Leste South Submarine Cable (TLSSC), North-West Cable System</sub>
- **Melbourne to Tasmania** — best 10.1ms against a 5.9ms floor; 8/17 paths direct (normally 6) <br><sub>Basslink, Bass Strait-1, Bass Strait-2</sub>
- **Perth to Jakarta** — best 63.9ms against a 29.5ms floor; 40 paths measured <br><sub>INDIGO-West, Australia-Singapore Cable (ASC)</sub>
- **Perth to Oman** — best 111.1ms against a 85.0ms floor; 2/4 paths direct (normally 2) <br><sub>Oman Australia Cable (OAC) · only system on this route</sub>
- **Perth to Singapore** — best 51.5ms against a 38.3ms floor; 7/64 paths direct (normally 22) <br><sub>INDIGO-West, Australia-Singapore Cable (ASC), Darwin-Jakarta-Singapore Cable (DJSC)</sub>
- **Sydney to Fiji** — best 37.6ms against a 31.5ms floor; 6/6 paths direct (normally 6) <br><sub>Southern Cross Cable Network (SCCN), Southern Cross NEXT</sub>
- **Sydney to Hawaii** — best 189.2ms against a 80.0ms floor; 2 paths measured <br><sub>Telstra Endeavour, Southern Cross Cable Network (SCCN), Hawaiki</sub>
- **Sydney to Honiara** — best 38.3ms against a 28.0ms floor; 2/2 paths direct (normally 2) <br><sub>Coral Sea Cable System (CS²) · only system on this route</sub>
- **Sydney to Japan** — best 99.1ms against a 76.7ms floor; 23/94 paths direct (normally 25) <br><sub>Australia-Japan Cable (AJC), Japan-Guam-Australia South (JGA-S)</sub>
- **Sydney to New Zealand** — best 23.4ms against a 21.1ms floor; 50/65 paths direct (normally 50) <br><sub>Southern Cross Cable Network (SCCN), Southern Cross NEXT, Hawaiki, Tasman Global Access (TGA) Cable</sub>
- **Sydney to Noumea** — best 22.4ms against a 19.3ms floor; 6/9 paths direct (normally 6) <br><sub>Gondwana-1 · only system on this route</sub>
- **Sydney to Port Moresby** — best 37.7ms against a 26.9ms floor; 3/6 paths direct (normally 3) <br><sub>Coral Sea Cable System (CS²), PIPE Pacific Cable-1 (PPC-1)</sub>
- **Sydney to US West Coast** — best 133.6ms against a 118.3ms floor; 282/302 paths direct (normally 283) <br><sub>Southern Cross Cable Network (SCCN), Southern Cross NEXT, Hawaiki, Telstra Endeavour</sub>

<sub>A route is a pair of places, not a cable: several systems serve most of these and IP routing does not reveal which one carried a packet, so a healthy route is not evidence that every cable on it is intact. A path counts as direct when it is within reach of the physical floor between the two places. Routes with no vantage at the far end are listed in latency_watch.yaml under `uncovered`.</sub>