Executive summary
- The Indigo West and Indigo Central systems suffered insulation breaches near Perth caused by an unidentified vessel, while the Australia-Singapore Cable (ASC) suffered a physical severance in Indonesian waters off Anyer [2].
- Winston Qiu of Submarine Networks reports that these disruptions eliminated 100% of direct low-latency marine capacity between Perth and Southeast Asia, forcing traffic onto high-latency transpacific detours [2].
- Repairs on the Australia-Singapore Cable (ASC) are currently delayed by Indonesian regulatory permitting and security approvals [2].
- Gulf Development and Singtel Group entered a strategic partnership to develop the Vietnam-Thailand-Singapore (VTS) cable system to support regional data center and AI services [1].
- A coalition including INDOI Ltd. (IOX) and Blue Trade Investments Limited announced the LuLu Coastal Cable System to connect Mombasa to Lamu across 500km of Kenya's coastline by Q2 2028 [6, 7].
- Orange and its partners unveiled the ReuNION subsea cable project to link La Réunion to South Africa by 2028 to replace the aging SAFE system [8].
Gulf Development and Singtel Group have entered a strategic partnership to develop and invest in new submarine cable connectivity between Thailand and Singapore [1]. The first initiative under this agreement is the Vietnam-Thailand-Singapore (VTS) cable system, which is intended to strengthen Thailand's digital infrastructure to support regional demand for data center and AI services [1].
Suspected interference and anchor drag
Winston Qiu of Submarine Networks reports that the Indigo West and Indigo Central systems suffered insulation breaches near Perth caused by an unidentified vessel [2]. Additionally, the Australia-Singapore Cable (ASC) suffered a physical severance in Indonesian waters off Anyer, with repairs currently delayed by Indonesian regulatory permitting and security approvals [2]. These disruptions eliminated 100% of direct low-latency marine capacity between Perth and Southeast Asia, forcing traffic onto high-latency transpacific detours [2].
In the Baltic region, a Russian captain and an Azerbaijani boatswain are on trial in Finland for an incident where the Turkish-owned cargo ship Fitburg dragged its anchor for at least 130 kilometers across the Gulf of Finland [3]. The dragging damaged eight cables and pipelines, including Elisa and Arelion lines, and prosecutors argue the crew knowingly denied the incident to the Finnish Border Guard [3]. Separately, reports from Reuters and telegraphindia.com claim that NATO allies and the US intercepted Russian vessels and submarines in the Arctic to foil potential plots to sabotage subsea cables [4, 5].
Indian Ocean Infrastructure Expansion
A coalition including INDOI Ltd. (IOX) and Blue Trade Investments Limited announced the LuLu Coastal Cable System, which will connect Mombasa to Lamu across 500km of Kenya's coastline [6, 7]. The system features a submarine cable and a parallel terrestrial route with a design capacity of 60 Tbps per fibre pair, with five landing stations including Vipingo SEZ, Kilifi, and Malindi [6, 7]. The project is expected to be ready for service in Q2 2028 and is intended to provide a fully protected coastal system to support hyperscale data centres and cloud services along the LAPSSET corridor [6, 7].
Separately, Orange and its partners unveiled the ReuNION subsea cable project to link the French overseas island of La Réunion to South Africa [8]. Supported by the European Union, the €93 million project will replace the aging SAFE (South Africa Far East) cable system, which is approaching retirement in 2027, 2028 [8]. ReuNION is scheduled for Ready for Service in 2028 and will feature a design capacity of 320 Tbps across 16 fiber pairs to support growing cloud and enterprise traffic demands in the Indian Ocean [8].
Philippine Infrastructure Investment and Submarine Cable Proposals
The three major Philippine telecom operators, PLDT, Globe Telecom, and Converge ICT, have allocated over $2.2 billion for capital expenditure in 2026 to support the country's digital transformation [9]. DICT Secretary Henry Aguda stated these investments are intended to improve connectivity and infrastructure as the country rolls out the Konektadong Pinoy Act and expands the National Fiber Backbone [9].
Additionally, the three companies formed a consortium to propose a $500 million domestic submarine cable system [9]. Globe Telecom also proposed a unified national policy for shared underground conduits as part of these infrastructure initiatives [9].
References
- Gulf and Singtel Group form strategic partnership to enhance submarine cable connectivity between Thailand and Singapore (Singtel, media centre)
singtel.com · Also reported by: Submarine Telecoms Forum, Light Reading - Fragility in the Indo-Pacific Connectivity: A Deep-Dive Analysis of the Perth, Singapore Subsea Outages and the Transpacific Resilience Paradox - Submarine Networks (Submarine Networks)
submarinenetworks.com - Captain and Boatswain Go on Trial in Finland for Anchor Dragging Incident (The Maritime Executive)
Published: 09 Sep 2026 · maritime-executive.com · Claim type: confirmed_fact · Subject: fault, investigation · Systems named: Elisa lines, Arelion lines · Vessels named: Fitburg · Jurisdictions: FI, EE, RU - How UK, Norway and US foiled Russian subsea cable sabotage plot deep in Arctic waters (telegraphindia.com)
telegraphindia.com - NATO allies foil Russian subsea cable sabotage plot (reuters.com)
reuters.com - INDOI Ltd. (IOX), Blue Trade Investments Limited and Partners Launch Lulu Cable System at ITW Africa 2026 (maravipost.com)
maravipost.com - Kenya coast gets first fully protected submarine cable system as LuLu launches (techtrendske.co.ke)
techtrendske.co.ke - Orange Builds ReuNION Subsea Cable Linking La Réunion to South Africa - Submarine Networks (Submarine Networks)
submarinenetworks.com - Philippine telcos set $2.2B for infrastructure investment in 2026 (Light Reading)
lightreading.com
Standing status
Operator-reported state (read directly from each operator's own status page, not summarised by any model):
- AusInternet — network status — INDIGO West
Status: partial service disruption; Fault: shunt fault; Fault location: 65km from Perth Cable Landing Station; Repair ETA: 26 Aug 2026 / 30 Aug 2026 with an ETR on 4 Sep 2026; Delayed until: August 25th / 2nd of October NBN POI 2PTH (Penrith; Repair vessel: repairing the Shunt Fault off Perth betwee; Planned maintenance: NBN POI 3DAD (Dandenong) NNI Rehoming Planned Maintenance Schedule / September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 4
as at 2026-09-10 00:09 UTC · https://ausinternet.com.au/status/ - Global Secure Layer — network status — INDIGO West
Status: partial outage; Fault: shunt fault
as at 2026-09-10 00:09 UTC · https://status.gslnetworks.com.au - SUBCO — INDIGO West — INDIGO West
as at 2026-09-10 03:50 UTC · https://sub.co/indigo-west/ - SUBCO — Oman Australia Cable, INDIGO Central, INDIGO West, SMAP
Status: monitoring
as at 2026-09-10 17:08 UTC · https://sub.co - Telstra — service status
Status: monitoring
as at 2026-09-10 07:22 UTC · https://www.telstra.com.au/exchange - Vocus — network status
Status: operational; Affected system: drum
as at 2026-08-31 01:33 UTC · https://www.vocus.com.au
Cable systems shown are those named anywhere on the captured page, matched against the systems tracked in geofences.yaml. A named system is not by itself a claim that it is the affected one.
Changes in the last 7 days:
2026-09-10 00:09AusInternet — network status — Planned maintenance: Indigo Central (Perth-Sydney) Shunt Fault Repairs Planned Maintenance → NBN POI 3DAD (Dandenong) NNI Rehoming Planned Maintenance Schedule2026-09-10 00:09AusInternet — network status — Planned maintenance: September 15, 2026 12:00AM - 2:00AM AEST September 14, 2026 2:00PM - 4 → September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 42026-09-10 00:09AusInternet — network status — Planned maintenance: September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 4 → September 16, 2026 11:00PM - 6:00AM AEST September 16, 2026 1:00PM - 82026-09-10 00:09AusInternet — network status — Planned maintenance: September 16, 2026 11:00PM - 6:00AM AEST September 16, 2026 1:00PM - 8 → September 17, 2026 11:00PM - 6:00AM AEST September 17, 2026 1:00PM - 82026-09-10 00:09AusInternet — network status — Planned maintenance: September 17, 2026 11:00PM - 6:00AM AEST September 17, 2026 1:00PM - 8 → October 2, 2026 10:00AM - 9:00AM AEST October 2, 2026 12:00AM2026-09-10 00:09AusInternet — network status — System named on page: INDIGO Central → INDIGO West2026-09-10 00:09AusInternet — network status — System named on page: INDIGO West → (removed)2026-09-09 16:11AusInternet — network status — Planned maintenance: Data Centres → Indigo Central (Perth-Sydney) Shunt Fault Repairs Planned Maintenance2026-09-09 16:11AusInternet — network status — Planned maintenance: September 15, 2026 12:00AM - 2:00AM AEST September 14, 2026 2:00PM - 4 → September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 42026-09-09 16:11AusInternet — network status — Planned maintenance: Indigo Central (Perth-Sydney) Shunt Fault Repairs Planned Maintenance → September 15, 2026 12:00AM - 2:00AM AEST September 14, 2026 2:00PM - 42026-09-09 16:11AusInternet — network status — Planned maintenance: September 16, 2026 11:00PM - 6:00AM AEST September 16, 2026 1:00PM - 8 → September 17, 2026 11:00PM - 6:00AM AEST September 17, 2026 1:00PM - 82026-09-09 16:11AusInternet — network status — Planned maintenance: September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 4 → September 16, 2026 11:00PM - 6:00AM AEST September 16, 2026 1:00PM - 82026-09-09 14:10AusInternet — network status — Planned maintenance: NBN POI 3CBN (Cranbourne) - NNI Rehoming Planned Maintenance Schedule → Data Centres2026-09-09 14:10AusInternet — network status — Planned maintenance: September 10, 2026 10:00AM - 10:00AM AEST September 10, 2026 12:00AM → Indigo Central (Perth-Sydney) Shunt Fault Repairs Planned Maintenance2026-09-08 16:10AusInternet — network status — Planned maintenance: Data Centres → NBN POI 3CBN (Cranbourne) - NNI Rehoming Planned Maintenance Schedule2026-09-08 16:10AusInternet — network status — Planned maintenance: September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 4 → September 16, 2026 11:00PM - 6:00AM AEST September 16, 2026 1:00PM - 82026-09-08 16:10AusInternet — network status — Planned maintenance: September 15, 2026 12:00AM - 2:00AM AEST September 14, 2026 2:00PM - 4 → September 16, 2026 12:00AM - 2:00AM AEST September 15, 2026 2:00PM - 42026-09-08 16:10AusInternet — network status — Planned maintenance: NBN POI 3CBN (Cranbourne) - NNI Rehoming Planned Maintenance Schedule → September 10, 2026 10:00AM - 10:00AM AEST September 10, 2026 12:00AM2026-09-08 16:10AusInternet — network status — Planned maintenance: September 10, 2026 10:00AM - 10:00AM AEST September 10, 2026 12:00AM → September 15, 2026 12:00AM - 2:00AM AEST September 14, 2026 2:00PM - 42026-09-08 14:11AusInternet — network status — Planned maintenance: NBN POI 3CAU (Caulfield) NNI Rehoming Planned Maintenance Schedule → Data Centres
Incident threads:
other— 68 documents, last 2026-09-10 (quiet 1d)perth_indigo_2026_08(INDIGO West, INDIGO Central) — 13 documents, last 2026-09-09 (quiet 2d)
Measured path state (RIPE Atlas traceroute, median across probes over 24h, no model involved):
- perth to singapore — ocean crossing 151.1ms; queuing 0.7ms; end to end floor 273.2ms, +71.9ms against its 21 day baseline; clean crossing (21 probe(s), 42 reading(s) excluded as below the corridor's physical floor)
- sydney to japan — ocean crossing 133.7ms; queuing 0.5ms; end to end floor 181.9ms, +39.1ms against its 21 day baseline; clean crossing (17 probe(s))
- sydney to nz — ocean crossing 27.8ms; queuing 0.2ms; end to end floor 34.4ms, steady against its 21 day baseline; clean crossing (8 probe(s))
- sydney to singapore — ocean crossing 151.8ms; queuing 0.7ms; end to end floor 223.2ms, +22.7ms against its 21 day baseline; clean crossing (22 probe(s), 1 reading(s) excluded as below the corridor's physical floor)
A corridor is a city pair, not a cable. Several systems serve each of these routes and IP routing does not reveal which one carries a packet, so a healthy corridor is not evidence that any particular cable is intact: traffic reroutes onto a survivor within seconds of a fault. Per-probe detail is in cablewatch segments.
Vessel review queue:
darwin_cpz_standing(North West Cable System, Timor-Leste South Submarine Cable System) — 2 candidate(s), top review priority 0.40sydney_cpz_standing(Australia Singapore Cable, Southern Cross NEXT, Hawaiki, Southern Cross Cable Network, Tasman Express, Tasman Ring, Japan Guam Australia -North, Japan Guam Australia -South) — 2 candidate(s), top review priority 0.35perth_cpz_2026_08(INDIGO West, INDIGO Central) — 2 candidate(s), top review priority 0.33